When swapping timezones, each ALL DAY event now crosses 2 days.



 
 
Thread Tools Search this Thread Display Modes
  #1  
Old September 29th 06, 09:56 PM posted to microsoft.public.outlook.calendaring
susanmarie
external usenet poster
 
Posts: 4
Default When swapping timezones, each ALL DAY event now crosses 2 days.

When swapping time zones, each ALL DAY event now crosses two days, ore one
additional day if the event was originally more than one day.

I need to communicate a resource calendar to a different time zone, so I
snag a picture of the screen. I need to change the time zone in order for
the times to appear correctly to the end user, but I need to change back to
my time zone after taking the screen shot. Each time I do this I have to go
back and alter EACH all day event TWICE.

Anybody have a fix?

Ads
  #2  
Old September 30th 06, 05:16 AM posted to microsoft.public.outlook.calendaring
Diane Poremsky [MVP]
external usenet poster
 
Posts: 12,991
Default When swapping timezones, each ALL DAY event now crosses 2 days.

The only fix is to not use all day events or not change the time zone.

--
Diane Poremsky [MVP - Outlook]
Author, Teach Yourself Outlook 2003 in 24 Hours
Coauthor, OneNote 2003 for Windows (Visual QuickStart Guide)
Need Help with Common Tasks? http://www.outlook-tips.net/beginner/
Outlook 2007: http://www.slipstick.com/outlook/ol2007/

Outlook Tips: http://www.outlook-tips.net/
Outlook & Exchange Solutions Center: http://www.slipstick.com
Subscribe to Exchange Messaging Outlook newsletter:



"susanmarie" wrote in message
...
When swapping time zones, each ALL DAY event now crosses two days, ore one
additional day if the event was originally more than one day.

I need to communicate a resource calendar to a different time zone, so I
snag a picture of the screen. I need to change the time zone in order for
the times to appear correctly to the end user, but I need to change back
to
my time zone after taking the screen shot. Each time I do this I have to
go
back and alter EACH all day event TWICE.

Anybody have a fix?



  #3  
Old October 2nd 06, 05:55 PM posted to microsoft.public.outlook.calendaring
susanmarie
external usenet poster
 
Posts: 4
Default When swapping timezones, each ALL DAY event now crosses 2 days

Obviously, this was not the answer I was hoping for, but I accept that it is
correct. Thanks Diane!

"Diane Poremsky [MVP]" wrote:

The only fix is to not use all day events or not change the time zone.

--
Diane Poremsky [MVP - Outlook]
Author, Teach Yourself Outlook 2003 in 24 Hours
Coauthor, OneNote 2003 for Windows (Visual QuickStart Guide)
Need Help with Common Tasks? http://www.outlook-tips.net/beginner/
Outlook 2007: http://www.slipstick.com/outlook/ol2007/

Outlook Tips: http://www.outlook-tips.net/
Outlook & Exchange Solutions Center: http://www.slipstick.com
Subscribe to Exchange Messaging Outlook newsletter:



"susanmarie" wrote in message
...
When swapping time zones, each ALL DAY event now crosses two days, ore one
additional day if the event was originally more than one day.

I need to communicate a resource calendar to a different time zone, so I
snag a picture of the screen. I need to change the time zone in order for
the times to appear correctly to the end user, but I need to change back
to
my time zone after taking the screen shot. Each time I do this I have to
go
back and alter EACH all day event TWICE.

Anybody have a fix?




 




Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
changing reoccuring event timezones.. Adam Outlook - Calandaring 0 August 11th 06 07:45 AM
Convert/transform multiple All-day Event on a single day onto multiple To Do element (with None Deadline setting if possible) Federico Oliosi Outlook - Calandaring 0 August 3rd 06 01:42 PM
All "all-day-event" events suddenly span two days. How do I fix? douglasnelson Outlook - Calandaring 1 July 25th 06 10:21 AM
Outlook and Red Crosses AlanHo Outlook - General Queries 0 June 9th 06 05:39 PM
Can I display how many days remain until an event, eg vacation? Mike P Outlook - Calandaring 0 May 15th 06 09:31 AM


All times are GMT +1. The time now is 12:35 PM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.Search Engine Friendly URLs by vBSEO 2.4.0
Copyright ©2004-2024 Outlook Banter.
The comments are property of their posters.